Prepare for the CPIM Exam with a comprehensive quiz that features insightful questions and real-time feedback. Enhance your knowledge and understanding of inventory and production management to pass your certification test with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What should occur in the MRP system if delivery dates are delayed?

  1. Prioritize existing orders

  2. Shift items to a later date to allow more time

  3. Ignore the changes as plans should remain static

  4. Replan to keep schedules updated

The correct answer is: Replan to keep schedules updated

In an MRP (Material Requirements Planning) system, if delivery dates are delayed, the most appropriate action is to replan to keep schedules updated. This approach is crucial because MRP systems are designed to respond dynamically to changes in demand, lead times, and supply conditions. When delivery dates change, replanning allows the system to adjust the production schedule and material requirements accordingly. Replanning can involve rescheduling production runs, adjusting safety stock levels, and communicating with suppliers and stakeholders about the changes. By updating schedules in response to the delays, the organization can better manage resources, reduce the risk of stockouts, and align production with current demand. Maintaining updated plans helps ensure operational efficiency and customer satisfaction, as it allows teams to proactively address potential issues before they escalate. Ignoring changes, prioritizing existing orders without considering the new timelines, or shifting items without an overall reassessment of the production plan would not effectively address the implications of the delayed delivery dates.